Hickman Road Trail

PROJECT

Hickman Road Trail

CLIENT

City of Hickman

LOCATION

Hickman, Nebraska

Project Details

Schemmer provided the City of Hickman with all services necessary to successfully complete the Hickman Road Trail Connector project. These services include surveying, environmental analysis, trail design, bridge design and geotechnical engineering. The trail is approximately 4,300 feet long and parallels Hickman Road. Additional permanent and temporary easements were required at certain areas along the project. A storm sewer system was designed to accommodate runoff approaching the trail as Hickman Road drains into ditches. The project was funded with federal TE funds, administered through the NDOT.